Bored pier inspections in Cobbitty

The footings under your home, checked while the holes are still open.

  • Holes drilled and cages in, concrete not yet ordered
  • About 1 hour on site
  • Report within 24 hours
Request a quoteLeave your details and an inspector rings you back today.

No obligation. We use your details for your quote and may contact you about it even if you don't finish.

Fully licensed & accredited

Stage1 of 7
When to bookHoles drilled and cages in, concrete not yet ordered
Time on siteAbout 1 hour on site
Inspected againstAS 2870, AS 3600, the geotechnical report and the engineer's footing design

What is included in a Cobbitty bored piers inspection

  • Each pier located to the footing plan
  • Hole width taken at the collar
  • Depth compared with the engineer and soil report
  • Base of each hole where it can be seen
  • Cage bar size, laps and starters
  • Spacers keeping steel off the sides
  • Loose spoil and fallen soil at the base
  • Water or seepage in the holes
  • Starter bars long enough to tie into beams
  • Any rock or fill noted while drilling
  • Clearance to boundaries and services
  • Engineer's sign off points listed
Why it matters here

Bored piers inspections on Cobbitty builds

Some Cobbitty lots sit on sloping ground falling towards the creeks and the Nepean, and those blocks are more likely to have piers drilled under the edge beams. Depth is the question that matters: the engineer sets it from the soil report, and once concrete goes in, nobody can measure it again. We check the holes, the cages and what is lying at the bottom of each one.

What we find at this stage in Cobbitty

  • Pier holes stopping short of design depth
  • Cages sitting against the soil without spacers
  • Loose spoil left in the base
  • Water collected in holes after rain
  • Starter bars too short for the beam

The other stages of a Cobbitty build

  1. Slab pre-pour inspection in Cobbitty2Slab pre-pourSteel tied and plumbing through, the day before concrete
  2. Frame inspection in Cobbitty3FrameFrame standing and trusses fixed, before wrap and roof sheeting
  3. Lock-up (pre-plaster) inspection in Cobbitty4Lock-up (pre-plaster)Roof on, windows and external doors in, before any plasterboard
  4. Fixing inspection in Cobbitty5FixingLinings up, doors and joinery fitted, painter not yet in
  5. Waterproofing inspection in Cobbitty6WaterproofingMembrane cured in the wet areas and on balconies, tiler not yet started
  6. Pre-handover (PCI) inspection in Cobbitty7Pre-handover (PCI)Build complete, a fortnight or so before the handover date

All construction stage inspections in Cobbitty →

Guides

Construction stage guides for Cobbitty

All guides →

Book a bored piers inspection in Cobbitty

Instant online pricing, or talk to the booking team on 1300 471 805.

FAQ

Bored piers inspections in Cobbitty: common questions

Does every Cobbitty home need bored piers?

No. Many sit on a slab with edge beams only. Piers appear where the engineer needs to reach firmer ground, often on sloping or filled lots.

How long does the pier inspection take?

Around an hour on a typical house, longer when there are many piers or the site is wet.

Which documents help with a pier check?

The engineering drawings and the soil report for your lot, so we can check depths and sizes against them.

Can water in a pier hole be a problem?

Yes. Concrete placed into standing water can be weakened at the base. It should be pumped out first.

Is the certifier checking piers too?

Footings are generally a critical stage inspection for the principal certifier. Our check is independent and written for you.

And if one of the holes turns out short of the design depth?

The report records it and the builder should confirm with the engineer before the pour. It is a quick fix with the rig still on site.

CallGet a Free Quote